Here is the filming schedule for our project - completed by Giorgio and Carrick
No. | Scene | Date | Location | People | Props | Equipment | Other |
1 | 1 Jaden's House | 16th December 2024 (Subject to Change) | Jaden's House | Giorgio - Director and Cameraman | Old Telephone | Camera BT Speaker Light | Location is far from our houses |
Carrick - Ast. Director |
Kaka - Ast. Cameraman | Grape Juice and Wine Glass | Traffic is a big issue |
Jaden - Actor |
2 | 2 Bus Stop | 17th December 2024 | Sentral Parkir Kuta | Giorgio - Director and Cameraman | Headphones Bus | Having to go off peak times to ensure an empty bus |
Kaka - Ast. Cameraman |
Jaden - Actor |
3 | 3 Beach | 18th December 2024 | Pantai Saba | Giorgio - Director and Cameraman | Ice Cream Umbrella | Have to work around private arrangements |
Kaka - Ast. Cameraman |
Jaden - Actor |
4 | 4 Bar | 19th December 2024 | Soteria Restaurant | Giorgio - Director and Cameraman | Beer Bottle and Glass
Car
Rain | Have to work around private arrangements |
Kaka - Ast. Cameraman |
Jaden - Actor |
Self-Reflection:
This is very helpful for the team to stay organized and on track with the tight schedule. Carrick was the spreadsheet expert so I let him took control for the writing. Me and my friend arranged how the team will complete the filming. I'm very happy how this turns out and I am fortunate to have a friend that understands how to create neat documents.